Tuesday's pour turned into a 6 hour disaster, what's your worst one?

We had a 40 yard slab in Phoenix where the mix showed up way too wet, and by the time we bull floated it, the whole thing started sagging near the edge forms. Ended up having to screed it twice and burn the surface with a power trowel just to get it to set before dark, and the client kept asking if we were done yet. Anyone else ever get a load from the plant that just fights you all day?
1 comments

Log in to join the discussion

Log In
1 Comment
craig.parker
“Too wet” from the plant usually means the slump was off, not the mix itself.